If you have received an email about an application for a charger at your property after submitting your Andersen survey, this is likely related to the DNO application we have made on your behalf.

  • EV charger installations require permission from your Distribution Network Operator.
  • Andersen will submit this application or notification as part of your installation process.
  • The DNO may then contact you directly to confirm that an application has been received.
  • This is a normal part of the process and usually does not require any action from you.
  • If the email says the DNO wants to carry out work at your property before installation, please contact Andersen straight away. Our team can then advise you on the next steps.